Quantcast

WC Minnesota News

Wednesday, November 6, 2024

CITY OF MOORHEAD: Project Update: SE Main|20 St|21 St Underpass Project

Underpass

City of Moorhead issued the following announcement.

The SE Main|20 St|21 St underpass project is approximately 75 percent complete. Recent unseasonably warm weather has been good for construction progress. Current 

construction focus has been the retaining wall along the Otter Tail Valley Railroad (OTVR) tracks. This wall is expected to be complete by spring of 2021 to allow the OTVR 

permanent track to be installed in May. Following that, the remaining bridge (BNSF over SE Main Ave) will be constructed, and should be complete by late summer. Then the 

permanent BNSF track would be constructed followed by the underpass roadway construction.

Beams for the remaining bridge were delivered to the site on December 10 - 11 and will be stored on site until installation in the summer of 2021. With typical weather and no other 

unforeseen circumstances, the underpass is anticipated to be open to traffic in the late fall of 2021. The railroad wye connection and the closure of 1 Ave S to through traffic would 

be completed in the summer of 2022.

There will be a break from active construction December 19 – January 4.

For more information on the SE Main|20 St|21 St Underpass Project, please see our current projects page.

City of Moorhead Engineering Department, 218.299.5390

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate